Cali-GrafCali-Graf
DataMarket dataLA CountyPermits

Solar permit time in Los Angeles County: days from application to issue in the county and four cities, 2023–2026

Cali-Graf · Published Nov 11, 2026 · Data as of Aug 31, 2026

Outside new construction, 79% of the residential solar permits issued in unincorporated Los Angeles County from January 2025 to August 2026 were the county's express permits, which the applicant issues online, and 86% of them were issued on the day of application. Projects that went to plan check waited a median of 16 days, and three in four had a permit within 37 days. In Glendale, Alhambra, El Monte and La Cañada Flintridge, permits issued through SolarAPP+ or a city express permit had a median wait of zero days; plan review took a median of 22 days in Alhambra and 55 days in La Cañada Flintridge.

79%
Express permits, unincorporated LA County
Share of residential solar permits outside new construction, Jan 2025 – Aug 2026
16
Days in county plan check
Median, application to issue
55
Days in plan review, La Cañada Flintridge
Median, application to issue
In this guide
Days to a permit, January 2025 to August 2026How many permits took the same-day pathDays in plan review by yearCheck a permit timeline against these numbersData limitsQuestionsMethodologySourcesHow to cite this page

Days to a permit, January 2025 to August 2026#

JurisdictionPermit pathPermitsIssued same dayMedian days3 in 4 within, days
Unincorporated LA CountyCEC list: Custom PlatformCounty express (self-issued online)3,17786%00
Unincorporated LA CountyCEC list: Custom PlatformPlan check8695%1637
GlendaleCEC list: Custom PlatformCity express permit79659%02
GlendaleCEC list: Custom PlatformPlan review (all building types)3381%2538
AlhambraCEC list: SolarAPP+ PlatformSolarAPP+12293%00
AlhambraCEC list: SolarAPP+ PlatformPlan review1071%2247
El MonteCEC list: SolarAPP+ PlatformSolarAPP+11786%00
El MonteCEC list: SolarAPP+ PlatformPlan review1250%3362
La Cañada FlintridgeCEC list: SolarAPP+ PlatformSolarAPP+16296%00
La Cañada FlintridgeCEC list: SolarAPP+ PlatformPlan review1440%5588
Lakewood, Cerritos, Westlake Village, Artesia, LomitaCEC list: Custom Platform — Cerritos, Artesia; SolarAPP+ Platform — Lakewood; Without Platform — Westlake Village, LomitaCounty express (self-issued online)35892%00

Residential solar permits issued from Jan 1, 2025 to Aug 31, 2026, by the permit path the jurisdiction records. Days — calendar days from the application date to the issue date; issued same day — 0 days; 3 in 4 within — the number of days within which three of four permits were issued. Glendale's regular solar permit type covers all buildings; the other regular types are residential. CEC list — the platform each jurisdiction reported to the California Energy Commission under SB 379 (data of Nov 2, 2026). Left out: permits for new construction, and permits later voided, canceled, withdrawn, denied or refunded (Data limits). Source: LA County EPIC-LA Case History, downloaded Sep 2, 2026; EnerGov permit portals of the four cities, copied Oct 17, 2026.

Download this table (CSV)

The same-day path carried 70% of Glendale's solar permits in these months, 53% of Alhambra's, 53% of La Cañada Flintridge's and 48% of El Monte's. SolarAPP+ permits were issued the same day 93% of the time in Alhambra, 86% in El Monte and 96% in La Cañada Flintridge; Glendale's express permit, 59%. Through the county's system, Lakewood, Cerritos, Westlake Village, Artesia and Lomita had 358 express permits, 92% of them issued the same day; their other solar permits are not counted here.

Have the design ready before the permit
Cali-Graf lays out panels on the roof from satellite imagery, models the battery under the Net Billing Tariff and builds the customer proposal.
Open Cali-Graf

How many permits took the same-day path#

Jurisdiction202320242025Jan–Aug 2026
Unincorporated LA County19%85%80%75%
Glendale13%59%72%66%
Alhambra0%2%45%68%
El Monte1%4%36%79%
La Cañada Flintridge0%18%50%60%

Share of residential solar permits issued through the same-day path — the county's express permit, SolarAPP+ or Glendale's express permit — by year of issue, new construction and voided permits left out. 2026 covers January to August. Source: LA County EPIC-LA; EnerGov portals of the four cities.

Download this table (CSV)

The first county express permit in the data was issued in August 2023; in 2024 these permits made up 85% of residential solar permits in unincorporated areas outside new construction, 80% in 2025 and 75% in January–August 2026. The first same-day permits appear in Glendale in October 2023, in El Monte in December 2023, and in Alhambra and La Cañada Flintridge in October 2024. SB 379 required cities of 50,000 people or more and counties of 150,000 or more to offer an online, automated solar permit by September 30, 2023, and cities of 5,000 to 50,000 by September 30, 2024.

Days in plan review by year#

Jurisdiction202320242025Jan–Aug 2026
Unincorporated LA County204,113 permits21535 permits17566 permits15303 permits
Glendale14408 permits20189 permits23240 permits2698 permits
Alhambra12192 permits16133 permits23.580 permits2127 permits
El Monte—records start Jun 202325107 permits27.5110 permits4815 permits
La Cañada Flintridge31211 permits43.578 permits51108 permits62.536 permits

Median calendar days from application to issue for solar permits that went to plan review, by year of issue, with the number of permits below each median; 2026 covers January to August. El Monte's plan-review records in its portal start with applications from June 2023, so its 2023 median is left blank. New construction and voided permits left out. Source: LA County EPIC-LA; EnerGov portals of the four cities.

Download this table (CSV)

In unincorporated areas the median plan-check wait fell from 21 days in 2024 to 15 in January–August 2026, after the number of county permits in plan check dropped from 4,113 in 2023 to 535 in 2024. In Glendale and La Cañada Flintridge the median wait in plan review grew every year from 2023: in Glendale from 14 days to 26, in La Cañada Flintridge from 31 to 62.5. El Monte's went from 25 days in 2024 to 27.5 in 2025; its 2026 median rests on 15 permits. Projects that meet the same-day criteria can skip review, so these figures describe the projects left for review; the records do not show how complex each one was.

Check a permit timeline against these numbers#

For a home in one of these jurisdictions, check first whether the project fits the same-day path. The county's guide says that a project that misses any item on the express eligibility list is submitted for plan check, and that added electrical work, such as a main service panel upgrade, needs its own electrical permit as well. For a project that goes to review, use the median as the typical wait and the three-in-four figure for planning, then add the utility's side: the April 2023 solar rush page has days from interconnection application to Permission to Operate in SCE's territory.

Data limits#

The county figures come from LA County's EPIC-LA case history as downloaded on Sep 2, 2026: unincorporated areas, plus express permits for the five cities that use the county's system for them. The city figures come from the public EnerGov portals of Glendale, Alhambra, El Monte and La Cañada Flintridge, copied month by month on Oct 17, 2026; the copy holds 97% of the permits the portals' monthly searches reported. The City of Los Angeles is not covered: the LADBS open data set that carries application dates holds building permits only, and in LADBS's older open data most solar permits were electrical permits. Other cities are not covered; Arcadia's portal, also on EnerGov, lists solar only under a large-system permit type that ends in 2024.

Days are calendar days from the application date to the issue date. They include any time the application waited on the applicant, for corrections or fees, so they are not a measure of the city's review alone. Only issued permits are counted, by the date of issue: a permit still in review on Aug 31, 2026 is not in the 2026 figures, so long waits in recent months are undercounted. The paths are not like-for-like: the same-day path is for projects that meet a list of criteria, and the rest go to review.

Solar for new construction is left out everywhere: it belongs to a building project, and its waits differ sharply from those of other solar permits. A solar permit counts as new construction when its application came within 3 years after an application for a new building, other than an accessory dwelling unit, on the same parcel; in the county, also when the address names a numbered lot in a new subdivision. From January 2025 to August 2026 that left out 1,267 permits: in plan review, 608 in unincorporated areas (2 days at the median), 74 in El Monte, 33 in Alhambra, 25 in La Cañada Flintridge and 18 in Glendale. In unincorporated areas, 129 of the permits left out were on parcels being rebuilt after the January 2025 Eaton and Palisades fires; solar on Eaton fire rebuilds in Altadena has its own page. La Cañada Flintridge's portal has no separate permit type for accessory dwelling units, so some of its new-building permits may be for them. Counting new construction, the county's express permits were 71% of its residential solar permits in those months. With them kept, the plan-review median would be 7 days in unincorporated areas, 17 in Alhambra and 62 in El Monte. With a one-year window instead, Alhambra's median would be 17 days, because its new-construction solar permits were filed more than a year after the building applications; the other medians move by at most 3 days. The five contract cities' express permits are not checked for new construction, since their building permits are not in the county data. Also left out: 203 permits issued from January 2025 to August 2026 and later voided, canceled, withdrawn, denied or refunded, and 3 permits with an issue date before the application date. The CEC list is what each jurisdiction reported; the CEC says it does not certify whether a platform meets SB 379.

How long does a residential solar permit take in Los Angeles County?

It depends on the jurisdiction and the path. From January 2025 to August 2026, the county's express permits and the cities' SolarAPP+ and express permits were mostly issued on the day of application. For homes outside new construction, plan check took a median of 16 days in unincorporated areas, and plan review from 22 to 55 days in the four cities.

Which of these jurisdictions use SolarAPP+?

Alhambra, El Monte and La Cañada Flintridge record SolarAPP+ permits and reported SolarAPP+ to the CEC. Unincorporated LA County and Glendale reported custom platforms; their same-day permits are the county's express permit and Glendale's express permit.

Why do some solar permits still take weeks?

Projects outside the same-day criteria go to plan review. In the county, a project that misses any item on the express eligibility list is submitted for plan check.

Methodology#

County permits are cases in LA County Public Works' EPIC-LA Case History layer with work class “Express Solar Roof Mount Residential” or “Express Solar Roof Mount Residential with ESS” (the same-day path; the case name gives the jurisdiction, such as “Lakewood Express”) or with case name “Unincorporated Solar” and work class “Roof Mount Residential” (plan check). The layer lists a case once per parcel or address it covers; each case number is counted once. Dates are converted to the Los Angeles calendar date. City permits are the records of the four EnerGov portals with these permit types: Glendale — “Express Residential Solar Photovoltaic (PV) Permit (Single Family Dwelling only)” and “Solar Photovoltaic (PV) Permit”; Alhambra — “PHOTOVOLTAIC - SolarAPP+” and “Solar Permit - Residential”; El Monte — “SolarAPP+ Residential Solar Permit” and “Solar Residential”; La Cañada Flintridge — “SolarAPP+” and “Solar Panel - RESIDENTIAL”. A permit counts in the year of its issue date. Exclusions are applied in this order, each permit counted once: statuses Void, Canceled, Cancelled, Permit Cancelled, Withdrawn, Denied, Rejected and Refunded; an issue date before the application date; new construction. New-building applications are, in the county, work class “New” under Building Residential (not flagged as an accessory dwelling unit), Multifamily, Mixed Use and Commercial, and “Tract Home”; in the cities, Glendale's “Building Combination (Single Family) - New”, “Building (Multi-family or Condominium) - New” and “Building (Commercial, Commercial and Mixed Use) - New”, Alhambra's “Building Residential New”, “Building Commercial New” and “Building Permit - Residential New Construction”, El Monte's “New Residential Building”, “New Multi Family Building”, “New Commercial Building” and its earlier “Building Residential (New)” type, and La Cañada Flintridge's “New - Building (RESIDENTIAL)” and “New - Building (NON-RESIDENTIAL)”; voided ones are not used. A year is left blank in the plan-review table when the jurisdiction's plan-review records start after January 1 of that year. Medians are over permits; for an even count the median is the midpoint of the two middle values.

Sources#

  1. Los Angeles County Public Works — EPIC-LA Case History layer, downloaded Sep 2, 2026. https://services.arcgis.com/RmCCgQtiZLDCtblq/arcgis/rest/services/EPIC-LA_Case_History_view/FeatureServer/0
  2. Los Angeles County Public Works, Building and Safety — Guide for Express Permit Application Types (express permits as semi-automated, self-issued permits; projects outside the eligibility list go to plan check). https://www.pw.lacounty.gov/bsd/lib/fp/Express%20Permits/Guide%20-%20Express%20Permit%20Application%20Types.pdf
  3. City of Glendale — EnerGov permit portal. https://glendaleca-energovweb.tylerhost.net/apps/selfservice
  4. City of Alhambra — EnerGov permit portal. https://alhambraca-energovpub.tylerhost.net/apps/selfservice
  5. City of El Monte — EnerGov permit portal. https://elmonteca-energovweb.tylerhost.net/apps/selfservice
  6. City of La Cañada Flintridge — EnerGov permit portal. https://lacanadaflintridgeca-energovpub.tylerhost.net/apps/selfservice
  7. California Energy Commission — Residential Solar Permit Program Status Dashboard (SB 379 requirements and deadlines) and its data, last updated Nov 2, 2026. https://www.energy.ca.gov/residential-solar-permitting-program-dashboard

How to cite this page#

Cali-Graf. “Solar permit time in Los Angeles County: days from application to issue in the county and four cities, 2023–2026.” cali-graf.com, updated Nov 11, 2026. https://cali-graf.com/guides/solar-permit-time-los-angeles-county/