Solar on Eaton fire rebuilds in Altadena: permits through August 2026

Cali-Graf · Published Nov 10, 2026 · Data as of Sep 1, 2026

Homes rebuilt after the Eaton fire do not have to install solar or a battery. Executive Order N-29-25, signed July 7, 2025, suspended that requirement for homes lost in the January 2025 fires, but the new home must still be solar-ready. Through August 2026, owners of 128 of the 5,281 Altadena parcels where the fire destroyed a home had applied for a solar permit, 80 of them with a battery. Of the 136 rebuilds that LA County marks as completed, 39 had one.

128
Burned parcels with a solar permit
Applied after the fire, through Aug 2026
29%
Completed rebuilds with solar
Solar permit on the parcel
62%
Solar permits with a battery
Energy storage in the permit
In this guide
Where the rebuild standsSolar comes late in the rebuildWhat solar-ready meansPlan the system for a rebuilt homeData limitsQuestionsMethodologySourcesHow to cite this page

Where the rebuild stands#

StageParcelsShareSolar permitBattery
No rebuild case yet1,96237%00
Rebuild application received2054%00
Zoning review cleared2695%00
Full building plans received4829%00
Building plans approved2865%11
Building permit issued3196%22
In construction1,62231%8660
Construction completed1363%3917

Altadena parcels where CalFire inspectors marked a single or multiple residence as destroyed in the Eaton fire, by the furthest stage of the parcel's rebuild cases in LA County's EPIC-LA permit system as of Sep 1, 2026. Solar permit — a residential solar or battery permit applied for on the parcel after the fire and not voided, canceled, withdrawn, denied or rejected; battery — one of those permits includes energy storage. Source: LA County EPIC-LA Case History, downloaded Sep 2, 2026; CalFire Damage Inspection (DINS) data.

Download this table (CSV)

Twenty months after the fire, 63% of the burned parcels had a rebuild case with the county and 39% had reached a building permit. 1,962 parcels had no rebuild case at all. Most of the active rebuilds were under construction — 1,622 parcels — and 136, 2.6% of the burned parcels, were finished.

Design solar for the reserved roof
Cali-Graf lays out panels on the roof from satellite imagery, models the battery under the Net Billing Tariff and builds the customer proposal.
Open Cali-Graf

Solar comes late in the rebuild#

QuarterFirst building permit issuedRebuild completedFirst solar permit filedWith a battery
2025 Q10021
2025 Q237000
2025 Q3222121
2025 Q43886116
2026 Q1567163016
2026 Q2541506035
2026 Q3 (Jul–Aug)319632321

Altadena parcels where the Eaton fire destroyed a home: the quarter when the parcel's first rebuild building permit was issued, when its rebuild was completed, and when its first residential solar or battery permit was applied for. 2026 Q3 covers July and August. Source: LA County EPIC-LA Case History, downloaded Sep 2, 2026.

Download this table (CSV)

Solar permits follow the building permit by months: on the 127 parcels that had both, the first solar application came a median of 181 days after the first building permit was issued, and half of them between 108 and 224 days. The county issued first building permits on 647 burned parcels in 2025 and 1,108 in the first half of 2026, while solar applications on those parcels rose from 2 in the first half of 2025 to 60 in the second quarter of 2026. Among parcels still in construction, 5% had a solar permit; among completed rebuilds, 29% did, and 17 of those 39 included a battery. Of all the solar permits filed on burned parcels since the fire, 62% include a battery.

The records cannot show why most owners have not filed for solar. The order made it optional, and because solar applications come months into construction, some homes still being built may yet add one.

What solar-ready means#

LA County's guide to the executive order lists what a rebuilt single-family home must still show on its plans when it skips solar: at least 250 square feet of roof reserved for a future array, wall space reserved for the inverter and metering equipment, a pathway for conduit from the electrical service to that roof area, and an electrical service of at least 200 amps with space for a two-pole breaker for the future system. Accessory dwelling units built with the main house get the same exemption and the same solar-ready rules. The same order also lets rebuilds follow the 2022 California Building Standards Code instead of the 2025 code.

A later order of Nov 24, 2025 made solar and battery upgrades eligible costs for insurance purposes for owners who have insurance proceeds available and choose to install them. These rules are as LA County described them in September 2025 and the California Department of Insurance in November 2025; we found no later change to either order as of Nov 10, 2026.

Plan the system for a rebuilt home#

A solar-ready home has the roof area, equipment space, conduit pathway and electrical capacity set aside for adding panels later. To size an array for the reserved roof, start with the solar production calculator; to size a battery for outages, use the battery backup calculator. Check any contractor's license and workers' compensation before signing.

Data limits#

The permit records are LA County's EPIC-LA case history as downloaded on Sep 2, 2026, so the counts stop at Sep 1, 2026; later permits are not included. They cover Altadena, an unincorporated community where the county issues permits. Burned homes with Pasadena or Sierra Madre addresses are left out because those cities issue most of their permits, and the Palisades fire is not covered: of its 5,021 parcels with a destroyed home, 78% were in Pacific Palisades, part of the City of Los Angeles, and 21% had a Malibu address, and those permits are mostly not in EPIC-LA. Counts are of parcels, matched by Assessor's parcel number: CalFire counted 6,112 destroyed homes and 9,419 destroyed structures of all kinds in the Eaton fire, and one parcel can hold several. A solar permit is an application: 125 of the 128 parcels had one issued and 36 had one completed by Sep 1, 2026. 5 parcels whose only solar permits were voided or canceled are not counted. A few early solar permits after the fire may cover a structure that survived on the same parcel. The rebuild stage is the county's own progress label.

Do I have to install solar when rebuilding after the Eaton fire?

No. Executive Order N-29-25, signed July 7, 2025, suspended the rooftop solar and battery storage requirements for rebuilding homes lost in the January 2025 Eaton and Palisades fires. The home must still be solar-ready, with roof space, wiring space and electrical capacity reserved for a future system. A later order of Nov 24, 2025 made solar and battery upgrades eligible costs for insurance purposes for owners who have insurance proceeds available and choose to install them.

How many Eaton fire rebuilds have solar?

In Altadena, 128 of the 5,281 parcels where a home was destroyed had applied for a solar permit by Sep 1, 2026, 80 of them with a battery. Among the 136 completed rebuilds, 39 had a solar permit.

Does solar-ready mean the home has panels?

No. It means the plans reserve space and capacity for panels later: for a single-family home, 250 square feet of roof, wall space for equipment, a conduit pathway and a 200-amp service with room for a solar breaker.

Does this cover the Palisades fire?

The executive order does. These permit counts do not: 78% of the parcels where the Palisades fire destroyed a home were in Pacific Palisades, part of the City of Los Angeles, which keeps its own permit records.

Methodology#

Burned parcels are the Assessor's parcel numbers of CalFire Damage Inspection (DINS) records for the Eaton incident with damage “Destroyed (>50%)”, structure category “Single Residence” or “Multiple Residence” and city “Altadena”. Rebuild cases are LA County EPIC-LA cases on those parcels whose disaster type is the Eaton Fire, excluding temporary-housing work classes; a parcel's stage is the furthest rebuild progress among its cases, in the county's order from “Rebuild Applications Received” to “Construction Completed”. The first building permit is the earliest issuance date among the parcel's Eaton-flagged permit cases (EPIC-LA module “PermitManagement”, temporary housing excluded); the completion quarter is the earliest completion date among its cases marked “Construction Completed”. Solar permits are cases with work class “Express Solar Roof Mount Residential”, “Express Solar Roof Mount Residential with ESS”, “Solar Photovoltaic” or “Storage Battery Systems” applied for on or after Jan 8, 2025, excluding cases that were voided, canceled, withdrawn, denied or rejected; a battery means the “with ESS” or “Storage Battery Systems” work class. Dates are in Pacific time.

Sources#

  1. LA County Public Works — EPIC-LA Case History (permit and planning cases, with disaster type and rebuild progress), downloaded Sep 2, 2026. https://services.arcgis.com/RmCCgQtiZLDCtblq/arcgis/rest/services/EPIC-LA_Case_History_view/FeatureServer/0
  2. CalFire — Damage Inspection (DINS) data, Eaton and Palisades fires, downloaded Sep 3, 2026. https://services1.arcgis.com/jUJYIo9tSA7EHvfZ/arcgis/rest/services/POSTFIRE_MASTER_DATA_SHARE/FeatureServer/0
  3. LA County Recovers — “Suspension of Solar Installation Requirements”, Sep 15, 2025. https://recovery.lacounty.gov/2025/09/15/suspension-of-solar-installation-requirements/
  4. LA County — Executive Order N-29-25 Implementation (solar and battery suspension, solar-ready requirements of Section 110.10, 2022 code option). https://file.lacounty.gov/SDSInter/lac/1191301_ExecutiveOrderN-29-25ImplementationSheet.pdf
  5. California Department of Insurance — “Southern California Wildfire Survivors Receive Good News in their Recovery and Rebuilding Process”, Nov 24, 2025: solar and battery upgrades as eligible costs for insurance purposes. https://www.insurance.ca.gov/0400-news/0102-alerts/2025/Southern-California-Wildfire-Survivors-R.cfm