The April 2023 solar rush in Los Angeles County's SCE territory: applications by month, 2022–2026
Homeowners in SCE's Los Angeles County territory submitted the interconnection applications for 11,135 home solar systems in March 2023 and 7,863 in April 2023, before the Net Billing Tariff took over for applications submitted on or after April 15, 2023. March was 5.7 times the monthly average of 2022. In May 2023 the count fell to 154. Applications submitted between Jan 1 and Apr 14, 2023 took a median of 154 days to reach Permission to Operate, against 27 days for those submitted in 2024 and 2025; most of that wait came before SCE deemed the application complete (a median of 122 days), and the step from complete to Permission to Operate took a median of 13 days.
In this guide
Applications by month#
Swipe to see all columns →
| Month received | Applications | NEM 2.0 | Net Billing | Median days to PTO |
|---|---|---|---|---|
| Jul 2022 | 1,769 | 1,769 | 0 | 14 |
| Aug 2022 | 2,217 | 2,217 | 0 | 11 |
| Sep 2022 | 2,337 | 2,337 | 0 | 14 |
| Oct 2022 | 2,436 | 2,436 | 0 | 7 |
| Nov 2022 | 2,305 | 2,305 | 0 | 7 |
| Dec 2022 | 2,656 | 2,656 | 0 | 6 |
| Jan 2023 | 3,880 | 3,880 | 0 | 54 |
| Feb 2023 | 5,693 | 5,693 | 0 | 127 |
| Mar 2023 | 11,135 | 11,135 | 0 | 161 |
| Apr 2023 | 7,863 | 7,819 | 44 | 198 |
| May 2023 | 154 | 1 | 153 | 156 |
| Jun 2023 | 209 | 1 | 208 | 133 |
| Jul 2023 | 317 | 0 | 317 | 95 |
| Aug 2023 | 451 | 6 | 445 | 73 |
| Sep 2023 | 475 | 2 | 473 | 44 |
| Oct 2023 | 599 | 0 | 599 | 34 |
| Nov 2023 | 691 | 2 | 689 | 22 |
| Dec 2023 | 707 | 12 | 695 | 23 |
| Jan 2024 | 994 | 1 | 993 | 13 |
| Feb 2024 | 929 | 0 | 929 | 5 |
| Mar 2024 | 1,077 | 0 | 1,077 | 5 |
| Apr 2024 | 1,081 | 0 | 1,081 | 12 |
| May 2024 | 1,087 | 0 | 1,087 | 23 |
| Jun 2024 | 903 | 1 | 902 | 27 |
Residential solar interconnection applications in SCE's Los Angeles County territory by month of App Received Date, counting only applications whose systems later received Permission to Operate (PTO). NEM 2.0 and Net Billing — by the application's interconnection program (see Data limits). Median days to PTO — from submission to Permission to Operate. NEM expansion records are left out. The download covers January 2022 to June 2026. Source: California DG Stats, data through Aug 31, 2026.
Download this table (CSV) · Download every month, Jan 2022 – Jun 2026 (CSV)
The months before the deadline climbed steeply, from an average of 1,939 a month in 2022 to 11,135 in March 2023. After the deadline the market restarted from a low base: applications submitted in 2024 totaled 12,348 and in 2025 15,560.
The last two weeks#
Swipe to see all columns →
| Day, 2023 | Applications | Net Billing |
|---|---|---|
| Mon, Apr 3 | 574 | 0 |
| Tue, Apr 4 | 576 | 0 |
| Wed, Apr 5 | 678 | 0 |
| Thu, Apr 6 | 544 | 0 |
| Fri, Apr 7 | 550 | 0 |
| Sat, Apr 8 | 248 | 0 |
| Sun, Apr 9 | 157 | 0 |
| Mon, Apr 10 | 668 | 0 |
| Tue, Apr 11 | 677 | 0 |
| Wed, Apr 12 | 726 | 0 |
| Thu, Apr 13 | 936 | 1 |
| Fri, Apr 14 | 1,184 | 0 |
| Mon, Apr 17 | 5 | 2 |
| Tue, Apr 18 | 2 | 2 |
| Wed, Apr 19 | 4 | 4 |
| Thu, Apr 20 | 4 | 4 |
| Fri, Apr 21 | 5 | 5 |
| Mon, Apr 24 | 1 | 1 |
| Tue, Apr 25 | 9 | 9 |
| Wed, Apr 26 | 7 | 7 |
| Thu, Apr 27 | 7 | 7 |
| Fri, Apr 28 | 1 | 1 |
| Sat, Apr 29 | 1 | 1 |
Applications submitted each day from April 3 to April 30, 2023, that later received PTO; days with none are not shown. Net Billing — applications filed under a Net Billing interconnection program. Source: California DG Stats.
Friday, April 14, 2023 was the last weekday before the change, and 1,184 applications were submitted that day. From April 1 to 14 there were 7,817; from April 15 to 30, 46.
From application to connection#
Of the 28,525 applications submitted between Jan 1 and Apr 14, 2023, 80% reached Permission to Operate in 2023, 16% in 2024, 3% in 2025 and 1% in 2026 through August. Their median wait from submission to Permission to Operate was 154 days, against 27 days for applications submitted in 2024–2025.
The records date two steps along the way. The step from submission to the date SCE deemed the application complete — all required documents provided and no deficiencies found — took a median of 122 days for the rush, against 12 days for applications submitted in 2024–2025. The step from complete to Permission to Operate took a median of 13 days, against 4 days for applications submitted in 2022 and 5 days in 2024–2025.
Under the decision that set the deadline, an application counted for NEM 2.0 on its submission date if it was free of major deficiencies and included the required documents, even if it did not yet have the local building department's post-inspection notice; the final building permit sign-off was due within three years of submission. The records do not say why any one application waited.
Months without a tariff deadline: 2024 and 2025#
Swipe to see all columns →
| Month | 2024 | Share | 2025 | Share |
|---|---|---|---|---|
| Jan | 994 | 8.1% | 1,261 | 8.1% |
| Feb | 929 | 7.5% | 1,151 | 7.4% |
| Mar | 1,077 | 8.7% | 1,322 | 8.5% |
| Apr | 1,081 | 8.8% | 1,351 | 8.7% |
| May | 1,087 | 8.8% | 1,072 | 6.9% |
| Jun | 903 | 7.3% | 1,045 | 6.7% |
| Jul | 918 | 7.4% | 1,100 | 7.1% |
| Aug | 1,031 | 8.3% | 1,027 | 6.6% |
| Sep | 1,019 | 8.2% | 1,895 | 12.2% |
| Oct | 1,118 | 9.0% | 1,473 | 9.5% |
| Nov | 1,101 | 8.9% | 1,324 | 8.5% |
| Dec | 1,090 | 8.8% | 1,539 | 9.9% |
Applications by month of submission in 2024 and in 2025, residential solar in SCE's Los Angeles County territory, with each month's share of that year's applications. Source: California DG Stats.
In 2024 every month held between 7% and 9% of the year's applications. In 2025 the range was 7% to 12%: from September to December applications averaged 1,558 a month, against 1,166 in January–August, and September 2025, with 1,895, was the largest month of the two years. The records do not say why. One dated change falls at the end of that window: the federal Residential Clean Energy Credit is not available for property placed in service after December 31, 2025.
Check it against the whole market#
For the yearly totals, batteries and cities in this territory, see the overview of residential solar; for how the battery share changed after the tariff, see the battery attach rate page.
Data limits#
DG Stats lists only projects that reached Permission to Operate, so an application that was submitted and never built is not counted; the number submitted in the rush was higher than shown here, by an amount the data cannot tell. Applications still waiting for Permission to Operate on August 31, 2026 are not in the data either, so the latest months can be undercounted and the 2024–2025 median wait would be the same or higher if they were counted. The App Received Date is set automatically by SCE's portal when the application is submitted. The NEM 2.0 and Net Billing columns follow the Interconnection Program field. The separate NEM Tariff field shows NEM 2.0 on 510 applications submitted between April 15 and December 31, 2023, but 487 of them are filed under a Net Billing program; the two fields disagree, and the records do not say which is right. By program, 27 applications submitted in those months are under NEM 2.0; the records do not say why. NEM expansion records of existing systems are left out. The data covers SCE's territory only; LADWP and other municipal utilities are not in DG Stats.
When did the Net Billing Tariff start?
It applies to interconnection applications submitted on or after April 15, 2023, under California Public Utilities Commission Decision 22-12-056. An application submitted earlier kept NEM 2.0 if it was free of major deficiencies and included the required documents; the local building department's post-inspection notice could come later.
How many solar applications were filed before the deadline in Los Angeles County?
In SCE's part of the county, 28,525 applications submitted between Jan 1 and Apr 14, 2023 later reached Permission to Operate, 1,184 of them on April 14 alone. Applications that were never built are not in this count.
How long did connections take after the rush?
Applications submitted from January to April 14, 2023 took a median of 154 days to reach Permission to Operate, against 27 days for those submitted in 2024–2025. Most of the wait came before SCE deemed the application complete (a median of 122 days); the step from complete to Permission to Operate took a median of 13 days.
Is there a solar season in Los Angeles County?
Not a steady one in this data. In 2024 each month held between 7% and 9% of the year's applications; in 2025, between 7% and 12%, with September to December averaging 1,558 applications a month against 1,166 in January–August.
Methodology#
The population is every record in the California DG Stats Interconnected Project Sites data set for SCE (data through Aug 31, 2026; files dated Oct 9, 2026) with Service County “Los Angeles”, Customer Sector “Residential” and a Technology Type that includes photovoltaic, excluding records whose Interconnection Program contains “Expansion”, counted by App Received Date (submission). Days to PTO are App Approved Date minus App Received Date; medians are by month of submission. The two steps use App Complete Date, the date the application is deemed complete. The tariff follows the Interconnection Program field: programs with “NBT” in the name count as Net Billing, the other programs as NEM 2.0, and the few Disaster Relief records follow the NEM Tariff field. Monthly shares are of each calendar year's applications.
Sources#
- California Distributed Generation Statistics — Interconnected Project Sites data set, data through Aug 31, 2026. https://www.californiadgstats.ca.gov/downloads/
- California DG Stats — Interconnected Project Sites Data Key (Nov 4, 2026): App Received Date, App Complete Date, App Approved Date, NEM Tariff, Interconnection Program. https://www.californiadgstats.ca.gov/downloads/
- California Public Utilities Commission — Net Billing Tariff: D.22-12-056; applies to interconnection applications submitted on or after April 15, 2023. https://www.cpuc.ca.gov/industries-and-topics/electrical-energy/demand-side-management/customer-generation/nem-revisit/net-billing-tariff
- California Public Utilities Commission — Decision 22-12-056 (issued Dec 19, 2022), pp. 196–197 (interconnection application date for the NEM 2.0 sunset) and p. 245 (three years to submit the final building permit sign-off). https://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M500/K043/500043682.PDF
- Internal Revenue Service — Residential Clean Energy Credit: not available for property placed in service after December 31, 2025. https://www.irs.gov/credits-deductions/residential-clean-energy-credit
How to cite this page#
Cali-Graf. “The April 2023 solar rush in Los Angeles County's SCE territory: applications by month, 2022–2026.” cali-graf.com, updated Nov 11, 2026. https://cali-graf.com/guides/april-2023-solar-rush-los-angeles-county-sce/