SCE interconnection under Rule 21: request-to-PTO timelines and why the dates matter

Cali-Graf · Published Nov 19, 2026 · Data as of Aug 31, 2026

For most homes the wait for permission to operate is short. Of the new home solar systems on SCE's Net Billing Tariff in Los Angeles County that got PTO in July and August 2026, half got it within 7 days of the interconnection request without a battery and within 15 days with one; once SCE had a complete application, the median was 1 day. The slowest tenth waited 128 days or more without a battery and 162 with one. The dates matter beyond the wait: under the Net Billing Tariff, the request date sets the year of the export price table and of the ACC Plus adder, and the PTO date starts the 9-year lock-in of those prices.

7
Days from request to PTO, median, no battery, Jul to Aug 2026
SCE, Los Angeles County, net billing
15
Same, with a battery
Same records
4
Days from complete application to PTO, median, 2025
Same records
In this guide
Days from request to PTO, by quarterWhat the timelines showWhy the dates matter under net billingData limitsQuestionsMethodologySourcesHow to cite this page

Days from request to PTO, by quarter#

Quarter of PTOSystemsMedian days, no batteryMedian days, with batterySlowest 10% from, no batterySlowest 10% from, with batteryMedian days, complete to PTO
2024 Q12,8861561331223
2024 Q22,66923131211248
2024 Q33,040322016414212
2024 Q42,88812141761385
2025 Q13,05115392251563
2025 Q23,90417502071794
2025 Q33,5955211241553
2025 Q44,17815491391827
2026 Q14,32614411201655
2026 Q23,9717171761742
2026 Q3 (Jul–Aug)2,4927151281621

New residential solar systems on SCE's Net Billing Tariff in Los Angeles County, by quarter of permission to operate. Days from the application received date to the approved date (PTO) in California DG Stats; "slowest 10% from" is the 90th percentile; "complete to PTO" is from the date the application was complete. Additions to existing systems are not included. Source: California DG Stats, Interconnected Project Sites, data through August 31, 2026.

Download this table (CSV)

Track the interconnection dates that set the customer's prices
Cali-Graf applies the export price vintage of the request date and models the bill hour by hour.
Open Cali-Graf

What the timelines show#

- PTO follows quickly once the application is complete. In 2025, a complete application reached PTO in a median 4 days, while getting the application complete took a median 17 days from the request. Most of the wait comes before the application is complete, a stretch the records do not split between SCE's review and the applicant's paperwork. - Battery systems have waited longer since 2025. In every quarter from January 2025 the median wait with a battery was longer than without, mostly in the time before the application was complete; in 2024 it was shorter in the first three quarters and about the same in the fourth. - A long tail. In 2025, half of the 14,728 new Net Billing systems got PTO within 34 days of the request, but one in ten waited 172 days or more. - The NEM 2.0 backlog is over. The 4,769 NEM 2.0 systems that got PTO in 2024 had nearly all applied before April 15, 2023, when the Net Billing Tariff began, and waited a median 394 days; they no longer distort the figures.

Why the dates matter under net billing#

- The request date sets the vintage. For interconnection requests from July 1, 2024 through December 31, 2027, and for earlier requests that reached PTO after June 30, 2024, SCE assigns the export price table (EEC vintage) of the year the request was submitted, and the ACC Plus adder of that same year; a system with PTO by June 30, 2024 kept the table of its PTO year. - The adder is shrinking. For residential customers who are not equity customers, the ACC Plus adder is $0.016 per kWh for a 2026 request, $0.008 for 2027 and $0.000 from 2028. - PTO starts the lock-in. The vintage's prices are fixed for 9 years from the original PTO date, as long as the interconnection agreement stays in the original customer's name or passes to an eligible same party. The tariff also says that for systems with an original PTO date after December 31, 2027 the export prices change every year, so a request filed late in 2027 that reaches PTO in 2028 may not keep a fixed table. - Rule 21 governs the connection. The tariff requires the system to be interconnected and operated in parallel with SCE's system under SCE's Electric Rule 21.

Data limits#

DG Stats gives three dates for each system: application received, application complete and approved; the approved date is the permission to operate. The records do not show the reasons for delays, resubmissions or the date of the building department's final inspection. Systems are grouped by the quarter of PTO, so a quarter mixes requests from different months. SCE's Rule 21 steps themselves are not covered here.

How long does SCE take to give permission to operate?

For new home systems on net billing in Los Angeles County in July and August 2026, a median 7 days from the request without a battery and 15 days with one; 1 day once the application was complete.

Why do some PTOs take months?

In the records most of the wait comes before the application is complete; one in ten systems in 2025 waited 172 days or more.

Does the interconnection request date affect my export credits?

Yes. For requests from July 1, 2024 through 2027, SCE assigns the export price table and the ACC Plus adder of the request's year, fixed for 9 years from PTO.

Methodology#

California DG Stats' Interconnected Project Sites (data through August 31, 2026): SCE, Los Angeles County, residential, new systems with solar (not expansions), NEM tariff "NBT", permission to operate from January 1, 2024 to August 31, 2026; medians and 90th percentiles of the day counts by quarter and by whether storage is recorded. The tariff rules are from SCE Schedule NBT in SCE's tariff book as of October 1, 2026, each checked word for word.

Sources#

  1. California Distributed Generation Statistics — Interconnected Project Sites data set. https://www.californiadgstats.ca.gov/downloads/
  2. Southern California Edison — Schedule NBT, Net Billing Tariff. https://www.sce.com/regulatory/regulatory-information/tariff-books/rates-pricing-choices

How to cite this page#

Cali-Graf. “SCE interconnection under Rule 21: request-to-PTO timelines and why the dates matter.” cali-graf.com, updated Nov 19, 2026. https://cali-graf.com/guides/sce-interconnection-under-rule-21-steps-and-pto-timelines/