Main panel upgrades with solar and batteries in Los Angeles County, 2024–2026

Cali-Graf · Published Nov 13, 2026 · Data as of Sep 2, 2026

Of 8,308 new solar installs on existing homes in unincorporated Los Angeles County, Glendale, Alhambra and El Monte, 1,639 (20%) came with a main electrical panel upgrade. In the county, Alhambra and El Monte, where the permit says whether a battery is included, installs with a battery had one in 21% of cases and solar-only installs in 13%.

A panel upgrade shows in the permit records in two ways: written into the description of the solar permit ("MPU 225/200A", "main panel upgrade to 200A"), or as a separate electrical permit for a main panel or service upgrade at the same home. This page counts both, the separate permit when it was applied for between 180 days before and 90 days after the solar application.

20%
Solar installs with a panel upgrade
Four LA County jurisdictions, 2024–2026
21%
With a battery
Unincorporated LA County, 2024–2026
13%
Solar only
Unincorporated LA County, 2024–2026
In this guide
Panel upgrades by jurisdictionWith a battery and withoutBy year in unincorporated Los Angeles CountyData limitsQuestionsMethodologySourcesHow to cite this page

Panel upgrades by jurisdiction#

JurisdictionSolar installsWith a panel upgradeNamed on the solar permitSeparate electrical permitSame homes 2–3 years earlierMain breaker derate
Unincorporated LA County6,34819%1,21312%8%1.1%2%
Glendale1,39722%301—21%2.0%—
Alhambra27714%408%10%1.8%2%
El Monte28630%8522%11%—3%
All four8,30820%1,639—10%1.3%—

New residential solar installs on existing homes with a solar application from Jan 1, 2024 to Mar 31, 2026 and a permit issued by Aug 31, 2026. With a panel upgrade — named on the solar permit, or a separate electrical permit for a main panel or service upgrade at the same home (parcel or street address) applied for from 180 days before to 90 days after the solar application; under the share, the number of installs. Same homes 2–3 years earlier — the same check for separate permits, in a window of the same length ending two years before the solar application, where the jurisdiction's electrical records cover every month of it (El Monte's do not). Main breaker derate — named on the solar permit. In Glendale only 32% of solar permits describe the work; the rest carry the express permit's standard text, so a panel upgrade there shows only as a separate permit. Source: LA County Public Works EPIC-LA; EnerGov permit portals of Glendale, Alhambra and El Monte.

Download this table (CSV)

El Monte had the highest share, 30%, and Alhambra the lowest, 14%. Separate upgrade permits at the same homes two to three years before the solar application came to 1.3% across the four, against 10% in the window around it, so separate panel upgrades cluster around the solar application.

Size the system before the panel work
Cali-Graf lays out panels on the roof from satellite imagery, models the battery under the Net Billing Tariff and builds the customer proposal.
Open Cali-Graf

With a battery and without#

InstallsSolar installsWith a panel upgradeMain breaker derate
Unincorporated county: solar only1,43813%1811%11
Unincorporated county: solar with a battery4,91021%1,0323%125
County, Alhambra and El Monte: solar only1,62813%2041%11
County, Alhambra and El Monte: solar with a battery5,28321%1,1343%139

The same installs in unincorporated Los Angeles County, and in the county, Alhambra and El Monte together. With a battery — the county's energy storage work class, or a battery, energy storage or a battery brand named in the solar permit description. Glendale is left out: its standard permit text does not say whether a battery is included. Under each share, the number of installs. Source: LA County Public Works EPIC-LA; EnerGov permit portals of Alhambra and El Monte.

Download this table (CSV)

In unincorporated Los Angeles County, 21% of solar installs with a battery came with a panel upgrade, against 13% of solar-only installs, and 85% of the installs with an upgrade had a battery. A main breaker derate, a smaller main breaker in the existing panel, was named on 2% of the county's solar permits.

By year in unincorporated Los Angeles County#

Solar applicationSolar installsWith a batteryWith a panel upgradeUpgrade, with a batteryUpgrade, solar only
20243,40173%21%23%15%
20252,56383%17%18%10%
Jan–Mar 202638478%19%22%7%

New residential solar installs on existing homes in unincorporated Los Angeles County by the date of the solar application, with the share that had a battery and the share with a panel upgrade, overall and with and without a battery. Source: LA County Public Works EPIC-LA.

Download this table (CSV)

The share of the county's solar installs with a battery rose from 73% in 2024 to 83% in 2025, while the share with a panel upgrade fell from 21% to 17%. For solar-only installs the upgrade share fell in each period, from 15% in 2024 to 7% in January–March 2026. The permits do not say why.

Data limits#

A panel upgrade counts only when the solar permit names it or a separate electrical permit for it is on file at the same home within the window. An upgrade done under another permit type, or outside the window, or not described, is not counted, and a separate upgrade in the window done for another reason, such as an EV charger, is counted; the earlier-years column shows how often the same homes had one when no solar was being installed. The wording rules for an upgrade, a derate and a battery were checked against samples of permit descriptions read by hand.

Unincorporated Los Angeles County covers the areas outside incorporated cities; each city issues its own permits. Solar installs on new homes, including homes in new subdivisions and accessory dwelling units, are left out. La Cañada Flintridge is not included: its portal gives no description for solar or electrical permits.

How often does adding solar come with a main panel upgrade in Los Angeles County?

In unincorporated Los Angeles County, 19% of new solar installs on existing homes with a solar application from January 2024 to March 2026 had a main panel upgrade named on the solar permit or filed as a separate electrical permit close to it; across unincorporated Los Angeles County, Glendale, Alhambra and El Monte it was 20%.

Does adding a battery make a main panel upgrade more likely?

In the permit records, yes. In unincorporated Los Angeles County, 21% of solar installs with a battery came with a panel upgrade, against 13% of solar-only installs, from January 2024 to March 2026.

What is a main breaker derate on a solar permit?

A smaller main breaker installed in the existing main panel instead of replacing the panel. It was named on 2% of new solar permits for existing homes in unincorporated Los Angeles County from January 2024 to March 2026, against 12% that named a panel upgrade.

Methodology#

Solar permits are the residential permit types of the solar permit time page: in the county, EPIC-LA cases with case name "Unincorporated Express" and an "Express Solar Roof Mount Residential" work class, or "Unincorporated Solar" with "Roof Mount Residential"; Glendale's "Express Residential Solar Photovoltaic (PV) Permit (Single Family Dwelling only)" and "Solar Photovoltaic (PV) Permit", Alhambra's "PHOTOVOLTAIC - SolarAPP+" and "Solar Permit - Residential", and El Monte's "SolarAPP+ Residential Solar Permit" and "Solar Residential". Each county case number counts once, with every parcel and address of its rows. A solar install counts when it is issued by Aug 31, 2026, not voided, canceled, withdrawn, denied or refunded, not a removal and reinstallation, and not on a new home: no new building on the parcel in the three years before, no "#Lot" in the county address, and no subdivision lot, accessory dwelling unit or new construction in the description.

A panel upgrade on the solar permit is a description naming an MPU; an upgrade, replacement or change-out of the main panel, service panel, MSP, service or meter, with up to three words between; or a new main panel or MSP ("(N) 225A main panel", "new 200A MSP"), unless a negation such as "no" or "without" comes within three words before it, or "no" or "N/A" right after it. A subpanel, a solar panel or a main panel turned into a subpanel does not count. A separate permit is an issued electrical permit at the same home, by parcel number or by house number and street, whose description names an upgrade by the same rule or a main panel with its ampere rating that is not existing or derated, or whose type is Glendale's "New/Upgrade Service" or El Monte's "Residential Electrical Panel" when it is not for an accessory dwelling unit, a new building or temporary power. A derate is a solar permit description naming one. Dates are application dates in Los Angeles time; shares are over installs.

Sources#

  1. Los Angeles County Public Works — EPIC-LA Case History layer, downloaded Sep 2, 2026. https://services.arcgis.com/RmCCgQtiZLDCtblq/arcgis/rest/services/EPIC-LA_Case_History_view/FeatureServer/0
  2. City of Glendale — EnerGov permit portal. https://glendaleca-energovweb.tylerhost.net/apps/selfservice
  3. City of Alhambra — EnerGov permit portal. https://alhambraca-energovpub.tylerhost.net/apps/selfservice
  4. City of El Monte — EnerGov permit portal. https://elmonteca-energovweb.tylerhost.net/apps/selfservice

How to cite this page#

Cali-Graf. “Main panel upgrades with solar and batteries in Los Angeles County, 2024–2026.” cali-graf.com, updated Nov 13, 2026. https://cali-graf.com/guides/main-panel-upgrades-with-solar-los-angeles-county/