Same house, two utilities: LADWP net metering vs SCE net billing in numbers

Cali-Graf · Published Nov 17, 2026 · Data as of Oct 1, 2026

Without a battery, the same home with the same solar saves far more on LADWP than on SCE. A home that uses 9,000 kWh a year, with 5.3 kW of solar that makes as much as it uses, pays LADWP $317 a year instead of $2,907, 89% less; on SCE's Net Billing Tariff it pays $2,162 instead of $3,537, 39% less. A battery changes the picture on SCE, adding $1,318 a year to the saving, and adds nothing on LADWP. With a battery, the SCE home saves about as much in dollars, $2,693 a year against $2,590, because its bill before solar is higher, but it still pays more after solar: $844 against $317.

The difference is in how each utility counts solar sent to the grid. LADWP still nets it against the power the home takes, kWh for kWh, over each two-month bill, so solar exported in a bill period is worth the full tier price of the kWh it offsets; a surplus carried to later bills pays only part of their charges, on the LADWP bills checked. SCE's Net Billing Tariff, which covers solar connected since April 15, 2023, pays for exports at hourly export prices — at noon a median of $0.033 per kWh in 2027 — while every kWh taken from the grid is billed at the full TOU-D-PRIME price.

89%
Bill saved on LADWP, 9,000 kWh home with solar covering its use
Modeled, first year
39%
Bill saved on SCE's Net Billing Tariff, same home and solar
Modeled, first year
$1,318
Extra yearly saving from a 13.5 kWh battery on SCE (none on LADWP)
Modeled, first year
In this guide
Yearly bill before and after solarWhy a battery pays on SCE and not on LADWPData limitsQuestionsMethodologySourcesHow to cite this page

Yearly bill before and after solar#

Home, yearly useLADWP, no solarLADWP, solarLADWP savedSCE, no solarSCE, solarSCE saved
6,000 kWhsolar 50% of use, 1.8 kW$1,740$91348%$2,230$1,67425%
6,000 kWhsolar 80% of use, 2.8 kW$1,740$42176%$2,230$1,52032%
6,000 kWhsolar 100% of use, 3.5 kW$1,740$22387%$2,230$1,43136%
6,000 kWhsolar 100% of use, 3.5 kW, battery$1,740$22387%$2,230$30586%
9,000 kWhsolar 50% of use, 2.6 kW$2,907$1,52947%$3,537$2,56028%
9,000 kWhsolar 80% of use, 4.2 kW$2,907$76474%$3,537$2,30135%
9,000 kWhsolar 100% of use, 5.3 kW$2,907$31789%$3,537$2,16239%
9,000 kWhsolar 100% of use, 5.3 kW, battery$2,907$31789%$3,537$84476%
12,000 kWhsolar 50% of use, 3.5 kW$3,914$1,98249%$4,794$3,40429%
12,000 kWhsolar 80% of use, 5.7 kW$3,914$94076%$4,794$3,06036%
12,000 kWhsolar 100% of use, 7.1 kW$3,914$34491%$4,794$2,86640%
12,000 kWhsolar 100% of use, 7.1 kW, battery$3,914$34491%$4,794$1,43570%

Yearly bill of the same modeled home on each utility, without city utility users tax, in 2027 at the rates in effect in late 2026. LADWP: residential rate R-1A with net metering. SCE: before solar TOU-D-4-9PM, with solar the Net Billing Tariff on TOU-D-PRIME, export prices of the latest published table and the ACC Plus adder for 2027 connections. Solar faces south at a 20° tilt with typical-year weather of Van Nuys; battery — 13.5 kWh usable. Saved — share of the bill without solar. Source: Cali-Graf engine.

Download this table (CSV)

With less solar the gap holds: solar that covers 50% of use cuts the LADWP bill by 47% and the SCE bill by 28%. On LADWP every kWh of solar is worth the same whether the home uses it or exports it; on SCE a kWh used at home is worth the full price and a kWh exported is worth the export price, so the saving depends on when the home uses power.

Model the home on its own utility
Cali-Graf bills the home hour by hour on LADWP net metering or SCE net billing, with or without a battery, and builds the customer proposal.
Open Cali-Graf

Why a battery pays on SCE and not on LADWP#

On SCE, a battery stores midday solar that would have been exported for a few cents and uses it in the evening, when PRIME charges its peak price; in late summer it also sends power to the grid in the evening hours when export prices are high, up to $1.21 per kWh. That added $1,318 a year for the 9,000 kWh home. On LADWP's tiered rate there is no evening price to avoid, and net metering already credits exports at the full price, so shifting solar into the evening does not change the bill; there a battery is for backup.

Data limits#

This is one modeled home, not two real ones: hourly use from building-stock profiles of Los Angeles homes scaled to the yearly use shown, the same solar and weather on both utilities. LADWP rates are held at their October–December 2026 level and SCE's at those of October 1, 2026 for the whole of 2027. SCE export prices are those of the latest published table, for a system connected in 2027. City utility users taxes are left out, because they differ by city: LADWP's customers pay the City of Los Angeles' 10%, and SCE's cities set their own. SCE's California Climate Credit is left out too; it is the same with and without solar. The bills are for the first year; payback and system prices are not compared.

Is solar worth more with LADWP than with SCE?

Without a battery, yes, by a wide margin on the bill. In the model, a 9,000 kWh home with solar covering its use saves $2,590 a year on LADWP and $1,375 on SCE's Net Billing Tariff. With a battery, the SCE home saves $2,693, about as much in dollars, but ends the year with a higher bill, $844 against $317.

Does a battery save money on LADWP?

Not on the bill. LADWP's net metering already credits exported solar at the full price, and its standard rate has no evening peak price, so a battery does not lower the bill; it adds backup power.

Why is the SCE saving smaller?

Because SCE's Net Billing Tariff credits exported solar at hourly export prices, a median of $0.033 per kWh at noon, and bills every kWh taken from the grid at the full TOU-D-PRIME price, while LADWP nets exports against use kWh for kWh.

Methodology#

The home's hourly use is built by the Cali-Graf engine from NLR ResStock profiles of Los Angeles single-family homes with a similar seasonal shape, scaled to the yearly use; LADWP bills in six two-month periods and SCE in twelve months, so each utility's bills follow its own periods. Solar output is a PVWatts-type model with typical-year NSRDB weather at the center of ZIP code 91406 (Van Nuys), south-facing at a 20° tilt, sized so that a year's output is the share of use shown (1,698 kWh per kW a year). LADWP: rate R-1A in its zone for that ZIP, tier allowances for two-month bills, Power Access Charge, net metering with surplus carried as a credit at tier prices, as on LADWP bills. SCE: without solar TOU-D-4-9PM in baseline region 9; with solar the Net Billing Tariff on TOU-D-PRIME — imports at full prices, exports at the hourly export prices of the latest published vintage, the ACC Plus adder, monthly billing and the annual true-up. The battery charges from solar, holds charge for PRIME's peak and sells to the grid in hours when the export price is worth more than the import price; on LADWP it is held for backup. Taxes: the state energy surcharge is included, city utility users taxes are not. Amounts are rounded half up.

Sources#

  1. Los Angeles Department of Water and Power — Residential Electric Rates and Residential Adjustment Billing Factors; Net Energy Metering Guidelines. https://www.ladwp.com/account/understanding-your-rates/residential-electric-rates
  2. Southern California Edison — Schedule TOU-D (Advice 5897-E, effective Oct 1, 2026) and Schedule NBT, Net Billing Tariff. https://www.sce.com/regulatory/regulatory-information/tariff-books/rates-pricing-choices
  3. Southern California Edison — Solar Billing Plan export prices (Energy Export Credit tables). https://www.sce.com/customer-service-center/help-center/solar/solar-billing-plan/understanding-export-pricing
  4. NLR — ResStock 2025 Release 1, End-Use Load Profiles for the U.S. Building Stock. https://registry.opendata.aws/nrel-pds-building-stock/
  5. NLR — National Solar Radiation Database (NSRDB), typical meteorological year. https://nsrdb.nlr.gov/

How to cite this page#

Cali-Graf. “Same house, two utilities: LADWP net metering vs SCE net billing in numbers.” cali-graf.com, updated Nov 17, 2026. https://cali-graf.com/guides/ladwp-net-metering-vs-sce-net-billing/