Cali-GrafCali-Graf
Building-integrated solar panelTesla

Tesla SR72T2

42 cells, Solar Roof Module. 72 W in the CEC list.

CEC listed · Sep 13, 2021UL 61730Building-integrated (BIPV)Installed in 2 SoCal permits
  • Power (STC)72 WCEC nameplate
  • Efficiency≈14.7%calculated from area
  • %/°C Pmax−0.372CEC listing test
  • PTC / STC90.8%PTC 65 W (CEC)

Electrical ratings (STC)

CEC PV Module List (Oct 7, 2026) · Cali-Graf calculation
ModelPmaxVoc, VIsc, AVmp, VImp, AEfficiencyPTCCEC listed
SR72T272 W14.206.8011.306.30≈14.7%65 WSep 13, 2021
≈ efficiency = Pmax ÷ CEC-listed area 0.49 m².

Heat & cold behaviour

CEC PV Module List (Oct 7, 2026) · Cali-Graf calculation
CEC listing test
Pmax coefficient γ−0.372 %/°C
Voc coefficient β−0.266 %/°C
Isc coefficient α+0.037 %/°C
Operating cell temperatureNOCT 48.2 °C
Vmp coefficient ≈ γ − α (CEC); used only for the hot-roof voltage estimate.

Away from lab conditions — CEC listing test points

ClassPmax at NOCTVmp × Imp at NOCTPmax at 200 W/m²Low-light efficiency vs STC
72 W53.2 W10.54 V × 5.05 A14.1 W98%
Pmax = Vmp × Imp from the CEC listing; low-light efficiency = Pmax at 200 W/m² ÷ (20% of STC Pmax).

Inverter compatibility & string sizing

CEC PV Module List (Oct 7, 2026) · Cali-Graf calculation · NLR PVWatts v8
15.1 V
Voc when cold
per panel
9 V
Vmp when hot
per panel
Defaults come from NLR TMY weather (coldest hour, hottest modeled cell). Code calculations (NEC 690.7) use the ASHRAE extreme annual minimum, which is usually colder — enter it above. β is the CEC-measured coefficient; NEC 690.7 calculations use the datasheet value.
Integrated roof products are wired per the manufacturer’s system design.
SolarEdge and other optimizer-based systems size strings by the optimizer rules — use the manufacturer’s designer. Reference inverters: most named in SoCal permits since Oct 2024.

Expected production in Southern California

NLR PVWatts v8 · Cali-Graf calculation
CitykWh / kW / yrkWh / panel / yrkWh / system / yrSun, kWh/m²/day
Los Angeles1,67612111,7056.08
Palmdale1,83513212,8166.69
Chula Vista1,69612211,8456.11
Huntington Beach1,64311811,4755.89
Riverside1,69612211,8456.21
Santa Clarita1,72412412,0406.28
764Jan765Feb981Mar1,084Apr1,071May1,138Jun1,198Jul1,212Aug1,060Sep935Oct804Nov696DeckWh per month · Los Angeles
PVWatts models a standard roof-mounted module; integrated roof products are not modeled separately.
Estimate for comparison, not a quote: shading, roof orientation and local losses change real output. Roof mount, 20° tilt, south, 14% system losses.

Who installs SRxxT2 panels in SoCal

building permits · CSLB License Master
2
Permits naming this series
Mar 2022 – Sep 2022
1
Licensed installers
CSLB license on the permit
2
Jurisdictions so far
Los Angeles (1), LA County (unincorp.) (1)
Only installer and ZIP level is shown — no homeowner names, street addresses or permit numbers. Permits from LA County (unincorp.) come without a contractor license, so they count toward totals but not toward installers. Counts grow as more permit portals are loaded.

Questions & answers

How efficient is the Tesla SR72T2?

Calculated from the panel area (0.49 m²): about 14.7% for the 72 W class. 72 W over 0.49 m² equals about 147 W per square meter.

How much energy does one panel produce in Los Angeles or Palmdale?

PVWatts v8 with typical-year weather gives about 121 kWh per year per 72 W panel in Los Angeles and about 132 kWh in Palmdale (20° roof, facing south, 14% system losses).

How much power does it lose on a hot roof?

With γ = −0.372 %/°C, at a 77 °C cell temperature (hottest modeled hour in Palmdale) output is about 19.3% below the STC rating.

Who installs it in Southern California?

Building permits name this series 2 times (Mar 2022 – Sep 2022). The most active licensed installers are Tesla Energy Operations Inc.

Sources

  1. California Energy Commission — Solar Equipment Lists, PV Module List (snapshot Oct 7, 2026).
  2. NLR (formerly NREL) — PVWatts v8, NSRDB PSM v3 typical-year weather for Los Angeles, Palmdale, Chula Vista, Huntington Beach, Riverside, Santa Clarita.
  3. Building permits — LADBS, City of Los Angeles (Sep 2022); Los Angeles County Public Works (EPIC-LA, unincorporated areas) (Mar 2022). Equipment matched from permit descriptions by model number.
  4. Contractors State License Board — License Master (contractor names and license status), as of Oct 5, 2026.
  5. Cali-Graf calculations — formulas and inputs are shown next to each calculated value (efficiency from area, temperature-corrected voltages, string sizing, energy estimates).